Stage 1 Complete - Titles released - Sold Out
Stage 2 Complete - Titles released - Sold Out
Stage 3 Complete - Titles released - Sold Out
Stage 4 Complete - Titles released - Sold Out
Stage 5 Complete - Titles released - One Section Remaining
Stage 6A update – this work is currently ahead of schedule and you can see now that all the kerb and channel work has been completed. The work is expected to be finished at the end of January so that we can uplift the titles approx.. end of February 2019.
Stage 6B update – some of this work has been started and can overlap with 6A – construction is due to finish in June so titles should be ready approx.. End of July 2019.
Stage 7 update – this will be the final stage and see Spitfire drive connect all the way through to Aerodrome road. Also this will include the last reserve. We are expecting titles towards the end of November.